Rank | R.I. | Problems |
---|---|---|
1 | 0.67 | Difficulty to prove the entitlement of claims |
2 | 0.66 | Fail to timely notify the Engineer potential delays |
3 | 0.65 | Difficulty to identify damages associated with delays |
4 | 0.64 | Lack of staff who is expert in performing “time impact analysis” |
5 | 0.62 | Problems in proving that the situation is expected or unexpected |
6 | 0.56 | Difficult to detect problems as the schedule is not updated |