Table 11: Problems of the time extension claims.

Rank R.I. Problems
1 0.67 Difficulty to prove the entitlement of claims
2 0.66 Fail to timely notify the Engineer potential delays
3 0.65 Difficulty to identify damages associated with delays
4 0.64 Lack of staff who is expert in performing “time impact analysis”
5 0.62 Problems in proving that the situation is expected or unexpected
6 0.56 Difficult to detect problems as the schedule is not updated

Wclaim = 0.546 Wvalue = 0.463