Rank | R.I. | Problems |
---|---|---|
1 | 0.58 | Inaccessibility of documents submitted with notice |
2 | 0.56 | No standard format of notice |
3 | 0.53 | Queries back due to the ambiguities of notices |
4 | 0.50 | Inadequate time to thoroughly prepare due to high workload |
5 | 0.49 | Prescribed time in the contract is too short. |
6 | 0.48 | Unclear procedures in notice preparation |
7 | 0.45 | Unclear responsibility person to prepare the notice |
8 | 0.39 | Poor communication to submit a written notice |