No. |
Factor |
Mean |
Std. Deviation |
% of RII |
t-value |
P-value |
Rank |
Finance Factors |
Start-up cost (Company registration) |
4.53 |
0.610 |
90.59 |
20.671 |
0.000 |
1 |
Foreign currency fluctuation |
4.24 |
0.775 |
84.71 |
13.145 |
0.000 |
2 |
Access to finance during the execution of work |
4.15 |
0.815 |
82.94 |
11.603 |
0.000 |
3 |
Material and Equipment Factors |
Continuous abruption of construction material |
4.74 |
0.444 |
94.71 |
32.196 |
0.000 |
1 |
High and unstable prices of construction material |
4.47 |
0.610 |
89.41 |
19.876 |
0.000 |
2 |
Price manipulation and monopoly of construction material |
4.15 |
0.815 |
82.94 |
11.603 |
0.000 |
3 |
Human Resources Factors |
Nomination and recruitment policies for the team |
3.74 |
0.785 |
74.71 |
7.729 |
0.000 |
1 |
Policies to maintain staff stability |
3.65 |
0.877 |
72.94 |
6.084 |
0.000 |
2 |
Lack of interest of qualified people to join the work |
3.53 |
1.126 |
70.59 |
3.877 |
0.000 |
3 |
Management Skills Factors |
The lack of clarity of vision and the difficulty of developing a strategic plan far away |
3.62 |
0.978 |
72.35 |
5.209 |
0.000 |
1 |
The need for a permanent marketing system and skills |
3.32 |
0.969 |
66.47 |
2.754 |
0.008 |
2 |
The need for professional consultants in the field of construction |
3.29 |
0.899 |
65.88 |
2.699 |
0.009 |
3 |
Communication and Work Relations Factors |
Involvement of the owner in the details of the execution of the work |
3.59 |
0.738 |
71.76 |
6.575 |
0.000 |
1 |
Complexities of dealing with suppliers |
3.44 |
0.817 |
68.82 |
4.451 |
0.000 |
2 |
Low turnout rates and difficult customer satisfaction |
3.38 |
0.847 |
67.65 |
3.723 |
0.000 |
3 |
Business Environment Factors |
The general economic situation is unstable |
4.47 |
0.657 |
89.41 |
18.451 |
0.000 |
1 |
Competitive nature of construction and contracting |
4.00 |
0.846 |
80.00 |
9.743 |
0.000 |
2 |
Corruption in some governmental and private institutions |
3.85 |
0.851 |
77.06 |
8.264 |
0.000 |
3 |