Table 3: Bn-1 operations from Nov 18 to Dec 31, 2009.

Date Operation Results
Nov 13, 2009 Drilling to the depth of 1870 m Well instability problems and deviation start to walk
Nov 14, 2009 Drilling to the depth of 1920 m Well instability problems
Nov 15 to 17, 2009 Wiper trip and reaming and change BHA Well instability problems
Nov18, 19 and 20 2009 Increase mud weight to 12 ppg mud and wiper trips,
Loss Circulating Materials (LCM) commenced.
Problems in well stability not solved
Nov 20, 2009 Rig up Super Combo and start Run # 1 for logging Logging performed from 1473 m upward only due to that bridge
Nov 20 to Nov 30 2016 Run # 2,3 and 4
Wiper trips and reaming
Problems in well stability not solved and in increase
Nov 30; 2009 Fishing of wire line logging tools failed
Dec 1, 2009 Opening the well to 12 ¼´´ to 1750 m top of the fish
Dec 2,3 and 4 2009 Fishing operating, wiper trips and reaming Fishing failed
Hole problems not solved
Dec 5 Start side tracking and drilling to 1929 m with 12 ¼´´ BHA
Dec 5 to Dec 10 Ream and wiper trips Hole problems not solved
Dec 11, 2009 First, run of casing 9  5/8´´ Failed at 1318 m due to the bridge.
Dec 12 to Dec 31 To attempts of casing running, many wiper trips and reaming Casing failed. Well instability problems not solved